Q1 Fast Start plan

The kickoff ends at lunch on Day 3; the work it was meant to start begins the Monday after. This plan puts an owner and a measure on each of the first 13 weeks, from the Monday-after email to the day-90 readout, so the follow-through is on the calendar before anyone boards a plane. Fill in your own baselines and targets before the event, not after.

Lock before the kickoff

Week by week

Day 1 is the first Monday back, so week 1 is days 1–7 and day 90 falls in week 13. The sample assumes a 30-day Fast Start window; extend the rows if yours runs longer.

WeekFocusOwnerMeasure
Within 48 hours of the closeAttendee survey out; award photos sharedEventsSurvey sent; every winner has their photos
Week 1 (days 1–7)Monday-after email from the CRO; manager cascade kits delivered; Fast Start tracking liveCRO, events, enablement, RevOpsEmail sent on day 1; a kit with every manager; first weekly Fast Start report out
Week 2 (days 8–14)Cascades held at team meetings; top-priority on-demand clips published; vendor retros heldManagers, enablement, eventsEvery team’s cascade confirmed by day 14; first clips live
Week 3 (days 15–21)Day 3 Q1 plans revisited in one-on-ones; certification raised by every managerManagersPlans reviewed; certification completion by team, sent to managers weekly
Week 4 (days 22–28)Certification push; Fast Start standings shared by teamEnablement, RevOps, managersCompletion by team; Fast Start activity against the same window last year
Week 5 (days 29–35)Day 30: certification deadline, remaining clips published, Fast Start window closes, first readoutEnablement, RevOps, eventsCertification completion; Fast Start activity and pipeline created per rep in the first 30 days
Week 6 (days 36–42)“Kickoff, six weeks later” segment at the all-hands: final Fast Start standings and winners namedCRO, eventsWinners named and prizes on their way; one rep shows how they used a new play
Week 7 (days 43–49)Day 45: final invoices reconciledEvents, financeFully loaded cost per head confirmed
Week 8 (days 50–56)Missed-certification follow-up; the two-hour kickoff path added to new-hire onboardingEnablement, managersEveryone certified or handled under the agreed policy; Q1 hires enrolled
Week 9 (days 57–63)Day 60: pipeline readout against baseline; pulse surveyRevOps, eventsPipeline created per rep in the first 60 days against the baseline; pulse answers on what people have used
Weeks 10–12 (days 64–84)Q1 QBRs and forecast calls reference the kickoff priorities by name; the theme stays on dashboards and team channelsSales leaders, managersKickoff priorities on every QBR agenda
Week 13 (days 85–91)Day 90: full results to the CRO and CFO; next year’s decisionsEvents, RevOpsOne-page scorecard, green, yellow, or red against the targets set in advance

Manager cascade

For every first-line manager. Enablement tracks it by team.

Fast Start reporting

Fill in baselines and targets before the kickoff and report every row on the same day each week. Keep any influenced-pipeline number on its own line, labeled as influence, and never add it to a total.

MeasureBaselineTargetSourceOwner
Opportunities created per AE, first 30 daysSame 30-day window last yearSet before the kickoffCRMRevOps
First meetings held, first 30 daysSame 30-day window last yearSet before the kickoffCRMRevOps
New product attached to opportunitiesLast year’s Q1 for a comparable launch, or noneSet before the kickoffCRMRevOps, product marketing
Pipeline created per quota-carrying rep, first 30 daysAverage of the last two years’ same windowSet before the kickoffCRMRevOps
Pipeline created per quota-carrying rep, first 60 daysAverage of the last two years’ same windowSet before the kickoffCRMRevOps
Certification completion by day 30Last year’s rate, if there was oneShare of quota carriers, set before the kickoffLMSEnablement
Manager cascades confirmedNoneEvery team by day 14Manager confirmationsEnablement
“I know what I need to do in Q1 to hit my number”Last year’s survey, if it askedShare who agree, set before the kickoffPost-event surveyEvents